Which procurement option can be used with Design-Build?

Get ready for the Project Delivery Exam with our comprehensive test, featuring detailed multiple-choice questions, insights, and explanations. Enhance your readiness and boost your confidence for the big day!

The design-build procurement method is characterized by a single contractual agreement where both design and construction services are provided by one entity, promoting collaboration and streamlined communication. The best value total cost option is well-suited for this method as it allows project owners to evaluate proposals based on a combination of price and quality. This enables them to consider factors such as innovative design, construction methods, and overall project efficiency while still keeping an eye on the budget.

With the best value approach, decision-makers can select a contractor not solely based on the lowest bid but also based on how well the proposal meets their specific project goals and needs. This can lead to higher quality outcomes and reduces the risk of cost overruns, as it emphasizes the overall value delivered rather than just the initial expense.

In contrast, options such as lowest possible cost or time-based selection may not adequately capture the collaborative and integrated nature of the design-build approach, potentially leading to compromises in quality or project scope. Random selection lacks the necessary criteria to ensure that the chosen provider has the qualifications or ability to deliver the best project outcome.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy